2010 – Wreel 10

2010 – Wreel 10

60 Ton Cradle

  • Medium voltage project that consisted of work on four different platforms.
  • Installed repair piece of 3/C – #2/0 awg,  15 KV,  XLPE submarine cable and submarine splice near platform to clear the Safe Jack Area.
  • Installed new section of riser subsea at platform to replace damaged riser.
  • Installed repair piece of 3/C – #2 awg,  5 KV,  XLPE submarine cable and subsea splice between two platforms.
  • Provided R. T. Casey splice chambers for all subsea splices.
  • Replaced Oil Switch and Transformer with LBOR Switchable Transformer on platform.
  • Completed  Incident Free.